In the contract administration process, what is the typical step after a change directive is issued if the parties reach agreement on change terms?

Get ready for the NCARB Continuum Education Exam with our educational quizzes. Prepare effectively with multiple choice questions, detailed hints, and explanations. Boost your confidence and pass your test!

Multiple Choice

In the contract administration process, what is the typical step after a change directive is issued if the parties reach agreement on change terms?

Explanation:
When a change directive is issued, it instructs a change to be carried out during construction. If the owner and contractor then agree on the terms of that change, the agreed terms are formalized with a change order. The change order documents the revised scope, updates the contract sum, and adjusts the schedule as needed, becoming part of the contract documents and authorizing the change. Payment requests (pay apps) come after the work is performed under the change, while RFIs are used to seek clarification and substantial completion is a later milestone.

When a change directive is issued, it instructs a change to be carried out during construction. If the owner and contractor then agree on the terms of that change, the agreed terms are formalized with a change order. The change order documents the revised scope, updates the contract sum, and adjusts the schedule as needed, becoming part of the contract documents and authorizing the change. Payment requests (pay apps) come after the work is performed under the change, while RFIs are used to seek clarification and substantial completion is a later milestone.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy