Construction Change Directive (CCD) is used when:

Get ready for the NCARB Continuum Education Exam with our educational quizzes. Prepare effectively with multiple choice questions, detailed hints, and explanations. Boost your confidence and pass your test!

Multiple Choice

Construction Change Directive (CCD) is used when:

Explanation:
A Construction Change Directive is used to authorize a change to the work when the owner wants to proceed with the modification before the scope and price are finalized. It directs the contractor to perform the change so the project can keep moving, with the understanding that the final cost and schedule will be resolved later, typically through a Change Order after negotiations. This approach avoids delaying construction while you hammer out the details of what, how much, and when the change will cost. That’s why the best description is the owner issuing a directive to change the work prior to agreement on scope and price. The other scenarios describe changes that are already agreed, or different procurement steps, which do not fit the purpose of a Construction Change Directive.

A Construction Change Directive is used to authorize a change to the work when the owner wants to proceed with the modification before the scope and price are finalized. It directs the contractor to perform the change so the project can keep moving, with the understanding that the final cost and schedule will be resolved later, typically through a Change Order after negotiations. This approach avoids delaying construction while you hammer out the details of what, how much, and when the change will cost. That’s why the best description is the owner issuing a directive to change the work prior to agreement on scope and price. The other scenarios describe changes that are already agreed, or different procurement steps, which do not fit the purpose of a Construction Change Directive.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy